In order to track and report, Physical % Complete needs to be used with some customized fields.One technique requires three Number fields: one to reflect the total “weight” or “worth” of each individual task, one to measure the value of work in progress, and the third to convert that value into summary percentages.Note that while the individual rows seem to be equal, the summary row isn’t, especially at the Project Summary level.

microsoft project updating progress-63

Microsoft project updating progress

Far too often people arbitrarily track project performance through the “Percent (%) Complete” method with subjective estimates for “how finished” the project is.

Microsoft Project doesn’t work well with this since manually entering values into the % complete field logically cascades a cavalcade of calculations, which aren’t necessarily intuitive.

Customize the weighted worth field by clicking on the Tools menu, pointing to Customize, and clicking Fields.

In the Customize Fields dialog box, click on the Tasks radio button and select Number in the Type: drop-down data list.

In the Customize Fields dialog box, click the Tasks radio button and select Number in the Type: drop-down data list.

Click on Number3 in the Field list and, under the Calculation for task and group summary rows section, click the Use formula radio button.Figure 1: A template example showing a Physical % Complete field inserted in the Entry table.Few Project users understand that updating progress with the % Complete field simply records what portion of the timeline has been completed.Click on Number1 in the Field list and, under the Calculation for task and group summary rows section, click the Rollup: radio button and select Sum from the drop down data list. Figure 4: The Customize Fields dialog box showing settings for the Weighted Worth field.The Physically Finished Weight field determines its values through a formula that multiplies the Physical % Complete field by the Weighted Worth field.If longer tasks have the most resources assigned, they’ll drive the summary statistics.